How to Read a Government Solicitation

Read the scope, Section L, and Section M before you write. Then build a compliance matrix and decide whether to bid or pass.

Start with three parts of the package, not the title. Read what the agency wants done (the scope of work), what you must submit and how (the instructions), and how the agency will score you (the evaluation factors). On many federal RFPs, those last two are Section L and Section M. State and local packets often use the same three ideas under different headings. Read all three before you write or decide to bid.

Confirm what kind of notice you opened

The notice type tells you what job you actually have. A sources sought or an RFI is usually market research. Responding can matter. It is not, by itself, a contract you can win that day. An RFP asks for a proposal. An RFQ asks for a quote. Sources sought vs. RFI vs. RFP vs. RFQ separates them.

Federal opportunities are posted in Contract Opportunities on SAM.gov. Search is free, and you can usually read a notice before your registration is finished. You still need an active registration when the notice requires one. A practical search method is in how to find government contracts on SAM.gov.

The title on the notice is a label. Open the description and every attachment. Write down the response date and time zone, the question deadline if there is one, the place of performance, and any set-aside. Then read the three parts below.

The three parts that decide the bid

When a federal solicitation uses the Uniform Contract Format in FAR 15.204-1, the package is organized into lettered sections:

  • Section C is the description, specifications, or statement of work.
  • Section L is the instructions, conditions, and notices to offerors or respondents.
  • Section M is the evaluation factors for award.

FAR 15.204-5 is the official description of Section L and Section M. Not every federal buy uses that lettered format. FAR 15.204 says the uniform format need not be used for construction and architect-engineer contracts, among other exceptions. Commercial buys and many state and local solicitations also skip the letters. They still have the same three questions:

  1. What exactly is the government asking for?
  2. What must be submitted, in what form, by when?
  3. How will proposals be evaluated?

If you are short on time, read the instructions first so you do not build a file the portal will reject. You still need the scope before you decide bid or pass, and the evaluation factors before you decide what to emphasize.

How to read the scope of work

The scope, statement of work, or performance work statement is the job itself. Read it for:

  • The work, not the keyword in the title
  • The place of performance, and whether you can staff that site
  • The period of performance, option years, and start-date assumptions
  • Quantities, frequencies, hours, or service levels
  • Licenses, insurance, bonding, clearances, or certifications
  • Government-furnished property, and what you must provide
  • Any wage determination, specification, or drawing in an attachment

Attachments often hold the real requirement. A short description can point to a longer statement of work, a technical exhibit, or a pricing schedule in Section J or a similar attachments list. If you price the summary and ignore the exhibit, you are pricing the wrong job.

This is also where a bid or pass starts. If you cannot perform the work as written, or you cannot document a license or clearance the scope requires, record the reason and move on.

Section L: what you must submit, and how

Section L, or the “instructions to offerors” or “instructions to bidders,” is the assembly manual. FAR 15.204-5(b) says this section guides offerors in preparing proposals, and that the agency may require a specific format or separate volumes, such as administrative, management, technical, past performance, and pricing.

Copy out, line by line:

  • The due date, the clock time, and the time zone
  • The question deadline, which is almost always earlier than the due date
  • How to submit: which portal, how many files, what to name them, whether paper copies are also required
  • Page limits, font, margin, and file-type rules
  • Required volumes or sections, and what belongs in each one
  • Required forms, representations, and certifications (often in Section K, or a similar forms packet)
  • Whether a site visit or a pre-proposal conference is mandatory
  • How amendments will be issued, and how you must acknowledge them

A page limit is not a suggestion. A missing volume is not a small typo. Follow the instructions as written, even if a different outline would have looked better to you.

If a required item is due with the bid, plan the time to get it: bonds or insurance evidence, resumes, references, or key personnel, when the instructions ask for them up front. Do not assume you can send those after award unless the notice says so.

Section M: how you will be scored

Section M, or the evaluation criteria, is how the agency compares eligible proposals. FAR 15.204-5(c) requires the solicitation to identify all significant factors and subfactors that will be considered, and their relative importance.

FAR 15.304 adds rules that matter on many federal negotiated buys. The factors and their relative importance must be stated clearly; the rating method itself need not be disclosed. Unless a stated exception applies, the solicitation must also say whether all evaluation factors other than cost or price, when combined, are significantly more important than cost or price, approximately equal to it, or significantly less important than it. Price or cost is evaluated in every source selection, with a narrow exception in that same section. Quality is addressed through one or more non-cost factors, such as past performance, technical excellence, management capability, personnel qualifications, or prior experience. Past performance is evaluated in many negotiated competitive acquisitions expected to exceed the simplified acquisition threshold, unless the contracting officer documents why it is not an appropriate factor.

Read the weights, not just the factor names. If technical approach is significantly more important than price, a thin technical volume with a low number is not a strategy. If price is significantly more important, you still have to be acceptable under the non-cost factors. The lowest number is not always the rule. How to price a government contract bid explains the cost terms. It is not a rate sheet for your firm.

If past performance is a factor, read the exact request: how many examples, how recent, whether they must be federal, and what form they must take. If you have no federal examples, see past performance when you have none before you write a package you cannot complete.

If the evaluation factors are missing or too vague to use, ask a question by the question deadline, or treat the notice with caution. You cannot design a scored proposal against criteria the agency has not given you.

Build a compliance matrix before you write

A compliance matrix is a table that turns the notice into a checklist. Each row is one instruction or evaluation factor, where it lives in the notice, where you will answer it in the proposal, who owns it, and whether it is done.

At a minimum, include:

  • Every instruction about format, volumes, forms, and page limits
  • Every “shall” or mandatory requirement in the scope
  • Every evaluation factor and significant subfactor in Section M, or the equivalent criteria
  • Amendment items, once an amendment is issued

The matrix is a working tool. The solicitation is the authority. If the two disagree, the notice wins.

This is how you see a hole while there is still time to fix it: a missing resume, an unfilled form, a factor with no section pointing to it. Govacha’s proposal tools help you assemble the draft and check it against the notice before you submit.

Watch the calendar, the questions, and the amendments

Three dates matter more than the rest of the packet:

  • The question deadline
  • The proposal due date, including the time zone
  • The date of the latest amendment

Ask questions on time, in the manner the notice requires, when a conflict, a missing quantity, or a mismatch between the instructions and an attachment needs to be on the record. Do not rely on a phone call that is not written down.

Agencies amend solicitations. An amendment can change the due date, the scope, a form, or an evaluation factor. Download the current package from the official posting, not from a copy you saved on the first day, and acknowledge amendments the way the instructions require.

Treat the due date and time as exact. Read the late-submission language in the solicitation itself.

Decide bid or pass after you have read it

A saved notice is not a bid. After you have read the scope, the instructions, and the evaluation factors, make a decision:

  • Can you perform the work as written, at the place and for the period required?
  • Can you submit a complete, compliant package by the due date?
  • Can you document the experience, personnel, or past performance the factors actually ask for?
  • Can you price the work without guessing at a requirement you did not find?

If the answer is no, record the reason and pass. A pass with a reason is a result.

If the answer is yes, move the notice into a working list, assign owners, and build the matrix before anyone writes a narrative. Govacha’s contract search and pipeline keep that list, the deadlines, and each bid decision in one place. The longer walkthrough of a pursuit is on how it works. If you are just getting started, begin with new to government contracting.

Frequently asked questions

What are Sections L and M in a government RFP?

On many federal RFPs that use the Uniform Contract Format, Section L is the instructions for preparing your proposal, and Section M is the evaluation factors for award. The official descriptions are in FAR 15.204-5. Section C is usually the statement of work.

Do state and local solicitations use Sections L and M?

Often they do not use those letters. They still usually include a scope of work, instructions to bidders, and evaluation criteria. Read those three parts the same way, even when the headings differ.

What is a compliance matrix?

It is a table of the things the notice told you to include or the factors it will score, the section of your proposal where you answer each one, and whether that item is done. It helps a team find a missing requirement before the due time.

Should I start writing before I finish reading the solicitation?

No. Read the instructions, the scope, and the evaluation factors first, including the attachments and any amendments. Writing early often produces pages that do not match the required outline, the page limit, or the factors the agency will score.

Where are federal solicitations posted?

Federal contract opportunities are posted on SAM.gov. Registration there is free. State and local work is posted on agency and state portals, not in one single federal feed.

What if the evaluation factors are missing or unclear?

Ask a question by the deadline and in the way the notice requires. If the agency never states how it will evaluate offers, passing can be the right decision.

Start with a notice you can actually answer

Pick one live notice. Read the scope, the instructions, and the evaluation factors. Build a compliance matrix. Then decide bid or pass.

Start for free to keep that work in one place. If you want a walkthrough of the product, book a demo.